    A very common Revit question I am asked, is “how do I move the ground level of my project?”

    Below is a quick guide to specifying your ground level, without physically moving the project and changing the views on sheets.

     

    Manage tab> Project Location> Coordinates> Specify Coordinates at Point:

      

      

    Select the ground level line and specify elevation:

      

     

      

    Ground level still says 0.

       

    Select the ground level line and change the type to Shared Datum:

     

     

      

     

    Ground level now shows the Shared Datum levels:

      