by Justin Doughty
A very common Revit question I am asked, is “how do I move the ground level of my project?”
Below is a quick guide to specifying your ground level, without physically moving the project and changing the views on sheets.
Manage tab> Project Location> Coordinates> Specify Coordinates at Point:
Select the ground level line and specify elevation:
Ground level still says 0.
Select the ground level line and change the type to Shared Datum:
Ground level now shows the Shared Datum levels: