    By Miles Nicholson

     

    Here’s how you can do it!

     

    Right click over the current activated project in the Project Manager

    Select Properties > Cross Reference tab.

     

    In the above example, the normal cross reference formula is “%S/%N”. On the Between Drawings add “ (%D)” onto the end of the normal method.

     

    Select    to accept any changes

    Right click over each drawing in the project > Properties > Drawing Properties

    Add the client drawing value into the Drawing field.

    Select   to accept any changes.

    Repeat on all other drawings

     

    Highlight all drawings in the project > right click and select Apply Project Defaults

     

    How to Update

     

    1)Title Block Update

    a) Right click over the project > Title Block Update

    b) Ensure the R Drawing (%D value) is selected

    Run on the entire project

     

    2)Cross Reference Update

    a) Select Schematic ribbon tab > Edit Components panel >  Component Cross-Reference

    Run on the entire project

     

    3. Update Signal reference 

    a) Select Schematic ribbon tab > Edit Wires/Wire Numbers panel  >  Update Signal References

    Run on the entire project

     

    The drawings will then be similar to: